Key Responsibilities
\n\n\n1) Planning & Coordination
\n\n- Interpret issued-for-construction (IFC) drawings , formwork shop drawings, and pour plans; develop method statements and work packs for each block/lift. \n
- Prepare daily/weekly look-ahead plans (materials, workforce, equipment) synced to concrete pour schedules and rebar readiness. \n
- Define formwork systems (traditional timber, modular steel/aluminum, climbing/slide forms, custom curved forms) based on structural geometry (spillway/chute, dam blocks, galleries, draft tubes, piers). \n
- Coordinate interfaces with rebar, embeds/inserts, water-stops, construction joints, cooling pipes, instrumentation and embedded metals. \n
- Plan lift heights, staging/scaffolding, access , and erection/dismantling sequences to optimize cycle time and safety. \n\n
- Lead erection, alignment, plumb, level, and curvature control per drawings; ensure camber/offsets where specified. \n
- Calculate and verify formwork pressures (rate of pour, concrete temperature, slump) and select adequate ties, walers, studs, bracing . \n
- Ensure form-release agents , surface preparation, joint sealing , and form tightness to prevent honeycombing and leakage. \n
- Implement thermal control measures (cooling pipes coordination, insulation, pour temperature limits) to maintain joint integrity and reduce thermal cracking. \n
- Oversee pre-pour inspections with QA/QC; close NCRs/snag lists; maintain as-built adjustments logs. \n\n
- Enforce HSE method statements , Job Hazard Analysis (JHA) , and Permit-to-Work for all formwork activities—especially at height, near water, night pours, and heavy lifts. \n
- Ensure scaffolding/working platforms are certified; maintain fall protection and restricted access during pour. \n
- Conduct toolbox talks , PPE checks, and lifting plan briefings; coordinate with lifting supervisor for panel handling and crane operations. \n\n
- Ensure dimensional accuracy: line, level, plumb, elevation , curvature/geometry for spillway/chute profiles; form alignment tolerance per project specifications. \n
- Verify construction joint preparation , keys , and waterstops placement; ensure embedment tolerances for anchors/inserts. \n
- Document pre-pour / post-pour checklists , inspection requests (IRs) , and maintain redline/as-built records. \n\n
- Track material inventories (plywood/ply board, steel/aluminum panels, H‑frames, props, ties, clamps, walers, consumables). \n
- Control formwork damage rates , repair cycles, and reuse factor ; reduce wastage and optimize procurement. \n
- Manage workforce productivity and equipment utilization (cranes, vibrators, power tools). \n
- Support cost control with accurate Material Take-Off (MTO) and consumption reporting. \n\n
- Issue daily progress reports (erection/dismantling, inspections, pour readiness) and weekly performance dashboards . \n
- Maintain RFI/Clarification logs with design/engineering; track NCRs and Corrective Actions . \n
- Keep equipment/inspection/maintenance records for formwork systems and accessories.
2) Technical Execution
\n\n3) Safety, HSE & Compliance
\n\n4) Quality Assurance & Control
\n\n5) Resource & Cost Management
\n\n6) Documentation & Reporting
\n\n